List of Projects and Schedules

The listing below represents upcoming construction and other ongoing projects planned to be underway during the Five-year Capital Construction Plan.

Projects are listed in order of its estimated start date. 

All start and completion dates are subject to change.*
 

Project Name Estimated Start Anticipated Completion
Campus WiFi Improvements Current April 2017
Elm and Pine Halls Renovations May 2016 July 2017
Maple Hall Renovation May 2016 November 2017
Residence Dining Hall (RDH) Renovation June 2016 April 2017
Campus-Wide Generators August 2016 April 2017
Burson Renovation August 2016 September 2017
Student Counseling Center September 2016 August 2017
East Village Utilities October 2016 April 2017
Academic Complex Renovation: Phase 1 - Denny December 2016 August 2017
Student Union Deck Expansion May 2017 May 2018
Campus Circulation Improvements May 2017 August 2017
Scott Hall Renovation May 2017 July 2018
Campus Stormwater: Phase 2 - Toby Creek May 2017 October 2018
Campus Stormwater: Phase 1 - Davis Lake June 2017 September 2017
Cone Switch Gear Relocation June 2017 September 2017
Health and Wellness Center (HAWC) June 2017 June 2019
Parking Lots Revitalization June 2017 January 2018
Campus Infrastructure Renewal: Phase 1 - Atkins Library/McEniry Hall July 2017 September 2018
Facilities Operations/Parking Services Complex July 2017 July 2018
SAC IT Upgrade July 2017 October 2017
Cone UniversityCenter - HVAC modernization July 2017 November 2017
Charlotte Research Institute (CRI) Entrance Improvements July 2017 December 2017
Foundation Annex Office Building Uplift July 2017 December 2017
Academic Complex Renovation: Phase 2 - Macy and Barnard August 2017 May 2018
Belk Plaza Revitalization September 2017 January 2018
Sycamore Hall September 2017 July 2018
Career Center Renovation September 2017 May 2018
Admissions and Visitors Center September 2017 December 2018
Reclaimed Water Project January 2018 June 2019
West Substation March 2018 July 2018
East Village Infrastructure (Traffic Improvements Phase 1) March 2018 December 2018
Lot 8 Expansion April 2018 July 2018
Academic Complex Renovation: Phase 3 - Garinger and Winningham May 2018 December 2018
Science Building August 2018 August 2020
Colvard North (5000 level) August 2018 July 2019
Moore Hall Renovation May 2019 July 2020
Colvard South (1000, 3000, and 4000 levels) August 2019 June 2020
Sanford Hall Renovation May 2020 July 2021

* Last Updated: Monday, March 20, 2017