The listing below represents upcoming construction and other ongoing projects planned to be underway during the Five-year Capital Construction Plan.

Projects are listed in order of its estimated start date. 

All start and completion dates are subject to change.*
 

Project Name Estimated Start Anticipated Completion
Campus WiFi Improvements Current June 2017
Elm and Pine Halls Renovations May 2016 July 2017
Maple Hall Renovation May 2016 November 2017
Residence Dining Hall (RDH) Renovation June 2016 September 2017
Campus-Wide Generators August 2016 September 2017
Burson Renovation August 2016 December 2017
Student Counseling Center September 2016   August 2017
Academic Complex Renovation: Phase 1 - Denny December 2016 December 2017
Scott Hall Renovation May 2017 July 2018
Student Union Deck Expansion June 2017 May 2018
Cameron/Poplar Lane Improvements (Facilities Operations Complex) June 2017 July 2017
Parking Lots Revitalization June 2017 January 2018
Health and Wellness Center (HAWC) July 2017 July 2019
Foundation Annex Office Building Uplift July 2017 December 2017
Campus Storm Water: Phase 1 - Davis Lake August 2017 November 2017
Academic Complex Renovation: Phase 2 - Macy and Barnard August 2017 May 2018
Facilities Operations/Parking Services Complex August 2017 July 2018
Campus Circulation Improvements August 2017 December 2017
Campus Infrastructure Renewal: Phase 1 - Atkins Library/McEniry Hall August 2017 November 2018
Belk Plaza Revitalization September 2017 January 2018
Cone Center Switch Gear Relocation September 2017 February 2018
Cone University Center - HVAC modernization October 2017 January 2018
Admissions and Visitors Center October 2017 January 2019
Sycamore Hall Renovation November 2017 September 2018
Charlotte Research Institute (CRI) Entrance Improvements December 2017 May 2018
Campus Stormwater: Phase 2 - Toby Creek January 2018 January 2019
Softball Indoor Training Facility February 2018 August 2018
Baseball Indoor Facility February 2018 August 2018
Student Activity Center (SAC) IT Upgrade April 2018 June 2018
Lot 8 Expansion April 2018 July 2018
West Substation May 2018 September 2018
Colvard North (5000 level) August 2018 July 2019
Career Center Renovation August 2018 February 2019
Science Building September 2018 October 2020
Academic Complex Renovation: Phase 3 - Garinger and Winningham September 2018 April 2019
Reclaimed Water Project January 2019 May 2019
East Village Infrastructure (Traffic Improvements Phase 1) March 2019 May 2020
Moore Hall Renovation April 2019 May 2020
Colvard South (1000, 3000, and 4000 levels) August 2019 June 2020
Sanford Hall Renovation May 2020 July 2021

* Last Updated: Monday, August 14, 2017