The Academic Complex Renovation project is to complete asbestos abatement, HVAC, sprinkler, fire alarm improvements and interior upgrades to include new paint, carpet and ceilings throughout.  Not all areas will receive new carpet.  Auditoriums will get new fixed seating, lighting, ceilings, drywall and acoustical treatments.

Cedar Move Guide

The work to be done will be completed in the following phases:

  • Phase 1:   Denny Building - Occupants will move to swing space December 19-21, 2016.  Targeted completion date December 2017.
  • Phase 2:   Macy Building - Occupants will move to swing space in the summer of 2017.  Targeted completion date May 2018.
  • Phase 2a: Barnard Building - Occupants will move to swing space in the summer of 2017.  Targeted completion date May 2018.
  • Phase 3:   Garinger/Winningham Buildings - Occupants will move to swing space in the summer of 2018.  Targeted completion date December 2018.